Evaluasi dan Peningkatan Kinerja Proyek menggunakan Metode Earned Value Analysis dan Metode Crashing
DOI:
https://doi.org/10.55606/jurritek.v5i2.9029Keywords:
Construction Management, Crashing, Earned Value Analysis, Project Performance, Time Cost EfficiencyAbstract
Construction project control requires careful planning to avoid delays and cost overruns. This study aims to evaluate the performance of the CBT Laboratory Building construction project at the Faculty of Medicine, Wahid Hasyim University, Semarang, in terms of cost and time using the Earned Value Analysis (EVA) method, and to analyze acceleration alternatives using the crashing method. The method used is a quantitative approach with a case study, based on project data such as the Budget Plan (RAB), S-curve, and work progress reports. The analysis was carried out using the Earned Value Analysis (EVA) method to assess project performance in terms of cost and time through indicators such as CV, SV, CPI, and SPI. Furthermore, an acceleration analysis was conducted using the crashing method to determine the optimal alternative for overcoming project delays by considering time and cost efficiency. The results of the Earned Value Analysis indicate that the project experienced delays and cost overruns, as shown by SPI < 1 and CPI < 1. The estimated project completion time increased to 227 days, longer than the initial plan of 217 days, while the estimated final cost reached RP 5,451,241,064.85, exceeding the initial budget. Acceleration efforts using the crashing method show that adding adding labor is more efficient than working hours (overtime), resulting in a project duration of 212 days with lower costs of RP 5,658,221,364.08. Thus, the Earned Value Analysis method is effective for evaluating project performance, while crashing can be a solution for acceleration by considering time and cost efficiency.
Downloads
References
Aditama, A., & Witjaksana, A. (2021). Analisis Pengendalian Biaya dan Waktu Proyek dengan Metode Earned Value Management. Jurnal Teknik Sipil, 10(2).
Cairurraziqin. (2025). Optimasi Kinerja Proyek Konstruksi melalui Integrasi Earned Value Analysis dan Metode Crashing. Tesis. Jakarta: Penerbit Publikasi Ilmiah.
Gido, J., Clements, J. P., & Baker, R. (2018). Successful Project Management. Cengage Learning.
Golmohammadi, A.-M., Shahabi, A., Shojaee, M., Hajizadeh Ebrahimi, F., & Abedsoltan, H. (2025). Enhancing Project Schedule Monitoring: Application of CUSUM and EWMA Memory Control Charts in Earned Schedule Method. https://doi.org/10.22059/aie.2025.389599.1937.
Kerzner, H. (2013). Understanding Best Practices. Project Management Best Practices. New Jersey: John Wiley & Sons, Inc.
Lamato, S., Sompie, B. F., & Walangitan, D. R. (2022). Analisis Kinerja Waktu dan Biaya pada Proyek Konstruksi dengan Menggunakan Metode Earned Value. Jurnal Sipil Statik, 10(1), 45-52.
Pangemanan, N. A., Sompie, T. P. F., Hombokau, C., & Kabo, D. R. G. (2025). Optimization of Duration of Shophouse Construction Project in Malalayang, Manado City. Jurnal Multidisiplin Madani, 5(5), 458–463. https://doi.org/10.55927/mudima.v5i5.290.
PMI (Project Management Institute). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide), 7th Edition. Pennsylvania: PMI.
Siregar, A. (2018). Estimasi Biaya dan Penyusunan Anggaran Proyek. Jakarta: Erlangga.
Soeharto, I. (1997). Manajemen Proyek dari Konseptual sampai Operasional. Jakarta: Erlangga.
Widyarso, R., Witjaksana, B., & Purnama, J. (2025). Analysis of Time and Cost Performance in Construction Projects Using the Earned Value Management Method. In Asian Journal of Engineering, Social and Health (Vol. 4, No. 4). https://ajesh.ph/index.php/gp.
Yonamastuti, D., & Aini, N. (2024). Integrasi Metode Earned Value Analysis (EVA) dan Crashing dalam Mengatasi Keterlambatan Proyek Konstruksi. Jurnal Manajemen dan Teknik Sipil, 8(1).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 Rishi Mardiningsih, Shafira Cournnyus Dwi Arta Gracia, Eko Muliawan Satrio, Kartono Wibowo

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

_001.jpg)




