Rekayasa Ulang Metode Pekerjaan Pengecoran dan Bekisting untuk Meningkatkan Kinerja Waktu dan Biaya Proyek Gedung Bertingkat

Authors

  • Dedi Achyadi Universitas Islam Sultan Agung Semarang
  • Kartono Wibowo Universitas Islam Sultan Agung Semarang
  • Soedarsono Soedarsono Universitas Islam Sultan Agung Semarang

DOI:

https://doi.org/10.55606/jurritek.v5i2.8363

Keywords:

Concrete Casting, Construction Duration, Formwork, Project Cost, Re-Engineering

Abstract

Time delays and cost overruns remain major problems in building construction projects, particularly in concrete structural works that dominate project duration and cost. This study aims to evaluate the application of re-engineering in concrete structural work methods on the time and cost performance of multi-storey building projects. A quantitative approach using a case study method was employed through comparative analysis between the existing method and alternative methods. The analyzed alternatives include ready-mix concrete with Sika Viscocrete 8007 admixture and semi-system formwork as Alternative I, ready-mix concrete with system formwork as Alternative II, and ready-mix concrete with Sika Viscocrete 8007 admixture combined with system formwork as Alternative III. The results show that all alternatives perform better than the existing method with a duration of 243 days. Alternative I reduced the duration to 208 days with cost efficiency of IDR 55,781,730 or 0.214 percent. Alternative II reduced the duration to 203 days with cost efficiency of IDR 187,553,261 or 0.724 percent. Alternative III achieved the best performance with a duration of 168 days, accelerating 75 days and providing the highest cost efficiency of IDR 243,334,991 or 0.941 percent. The study concludes that re-engineering effectively improves project time and cost performance, with Alternative III as the optimal method.

Downloads

Download data is not yet available.

References

Alshihri, S., Al-Gahtani, K., & Almohsen, A. (2022). Risk factors that lead to time and cost overruns of building projects in Saudi Arabia. Buildings, 12(7), 902. https://doi.org/10.3390/buildings12070902

Alvandi, B., Rosyati, R., & Abdu, M. (2021). Analisis perbandingan biaya pelaksanaan pekerjaan balok metode konvensional dan precast pada proyek Aspena Residence Batuceper. Structure, 3(1), 96. https://doi.org/10.31000/civil.v3i1.7156

Andriawan, E. (2020). Metode pelaksanaan pekerjaan kolom pada proyek Gedung Arandra Residence Jakarta.

Bigwanto, A., Widayati, N., Wibowo, M. A., & Sari, E. M. (2024). Lean construction: A sustainability operation for government projects. Sustainability, 16(8), 3386. https://doi.org/10.3390/su16083386

Daoud, A. O., Hefnawy, M. E., & Wefki, H. (2023). Investigation of critical factors affecting cost overruns and delays in Egyptian megaconstruction projects. Alexandria Engineering Journal. https://doi.org/10.1016/j.aej.2023.10.052

Idrees, S., & Shafiq, M. (2021). Factors for time and cost overrun in public projects. Journal of Engineering, Project, and Production Management. https://doi.org/10.2478/jeppm-2021-0023

Mohamed, A. S., Xiao, F., & Hettiarachchi, C. (2022). Project level management decisions in construction and rehabilitation of flexible pavements. Automation in Construction, 133, 104035. https://doi.org/10.1016/j.autcon.2021.104035

Mohammed, M., Shafiq, N., Elmansoury, A., Al-Mekhlafi, A.-B. A., Rached, E. F., Zawawi, N., Haruna, A., Rafindadi, A. D., & Ibrahim, M. (2021). Modeling of 3R (Reduce, Reuse and Recycle) for sustainable construction waste reduction: A partial least squares structural equation modeling (PLS-SEM). Sustainability. https://doi.org/10.3390/su131910660

Orobia, L. A., Nakibuuka, J., Bananuka, J., & Akisimire, R. (2020). Inventory management, managerial competence and financial performance of small businesses. Journal of Accounting in Emerging Economies, 10(3), 379–398. https://doi.org/10.1108/jaee-07-2019-0147

Priyo, M. (2021). Earned value management system in Indonesian construction projects. International Journal of Integrated Engineering. https://doi.org/10.30880/ijie.2021.13.03.005

Rachmawati, F., Mudjahidin, M., & Dewi Widowati, E. (2022). Work rate modeling of building construction projects using system dynamic to optimize project cost and time performance. International Journal of Construction Management, 24(2), 213–225. https://doi.org/10.1080/15623599.2022.2122265

Rossaty, R., Safitri, R. A., & Nabilah, S. A. (2023). Analisis perbandingan penggunaan bekisting konvensional dan bekisting alumunium terhadap biaya dan waktu (Studi kasus: Proyek Akasa Apartment Tower Kamaya, Bumi Serpong Damai, Tangerang Selatan). Structure, 4(2), 43. https://doi.org/10.31000/civil.v4i2.8062

Schützenhofer, S., Kovacic, I., Rechberger, H., & Mack, S. (2022). Improvement of environmental sustainability and circular economy through construction waste management for material reuse. Sustainability, 14(17), 11087. https://doi.org/10.3390/su141711087

Surono, A., & Rossyati, R. (2023). Faktor-faktor yang menyebabkan kegagalan bekisting pada proyek gedung sekolah St. Yohanes Pik2. Structure. https://doi.org/10.31000/civil.v5i2.10021

Terzioglu, T., Polat, G., & Turkoglu, H. (2021). Analysis of formwork system selection criteria for building construction projects: A comparative study. Buildings, 11(12), 618. https://doi.org/10.3390/buildings11120618

Umar, A. R., & Ranap Tua Naibaho, P. (2022). Proyek pembangunan jembatan rumah susun padat karya "Pengamatan pelaksanaan pekerjaan plat pada jembatan rumah susun padat karya." NUCLEUS, 3(1), 76–84. https://doi.org/10.37010/nuc.v3i1.791

Wibowo, M. A., Handayani, N. U., Mustikasari, A., Wardani, S. A., & Tjahjono, B. (2022). Reverse logistics performance indicators for the construction sector: A building project case. Sustainability, 14(2), 963. https://doi.org/10.3390/su14020963

Wyke, S., Lindhard, S., & Larsen, J. (2023). Using principal component analysis to identify latent factors affecting cost and time overrun in public construction projects. Engineering Construction and Architectural Management. https://doi.org/10.1108/ecam-02-2022-0189

Yanita, R., & Nurdiyanto, N. (2023). Perbandingan kinerja pengecoran antara concrete-bucket dan concrete-pump pada proyek bangunan bertingkat. Racic: Rab Construction Research, 8(2), 296–307. https://doi.org/10.36341/racic.v8i2.3639

Zhong, Q., Tang, H., & Chen, C. (2022). A framework for selecting construction project delivery method using design structure matrix. Buildings. https://doi.org/10.3390/buildings12040443

Downloads

Published

2026-05-01

How to Cite

Dedi Achyadi, Kartono Wibowo, & Soedarsono Soedarsono. (2026). Rekayasa Ulang Metode Pekerjaan Pengecoran dan Bekisting untuk Meningkatkan Kinerja Waktu dan Biaya Proyek Gedung Bertingkat. JURNAL RISET RUMPUN ILMU TEKNIK, 5(2), 21–30. https://doi.org/10.55606/jurritek.v5i2.8363

Similar Articles

1 2 3 4 5 6 7 8 9 > >> 

You may also start an advanced similarity search for this article.