Perancangan Mine Sequence untuk Mendukung Target Produksi Bulan April pada Tambang Nikel Laterit Pit Hill16 PT Hillconjaya Sakti
DOI:
https://doi.org/10.55606/jurritek.v5i2.8903Keywords:
Laterite Nickel Mining, Mine Sequence, Production Target, Productivity, Rolling PlanAbstract
This study is motivated by the discrepancy between production targets and actual field performance caused by dynamic operational conditions, such as equipment productivity and effective working time. The objective of this research is to redesign the production target and develop a more realistic mine sequence using a rolling plan approach at Pit Hill16. The method includes analyzing the productivity of loading and hauling equipment based on cycle time data, calculating effective working time, and determining production targets using the rolling plan method. Furthermore, mine sequence design is developed based on the adjusted production targets. The results indicate that the productivity of loading equipment is 241.98 BCM/hour for the EC480DL excavator and 123.27 BCM/hour for the EC210DL excavator, while hauling equipment productivity is 40.24 BCM/hour. The April production target based on the rolling plan is 275,913 BCM, which can be achieved through mine sequence design with a volume of 277,839 BCM, resulting in a difference of +1,926 BCM, still within acceptable planning tolerance. Therefore, the rolling plan approach is proven to produce a more adaptive and realistic mining plan under actual field conditions.
Downloads
References
Anwar, H., Setiawan, B., & Firmansyah, R. (2023). Estimasi kadar bijih nikel laterit menggunakan pendekatan geostatistik pada tambang terbuka. Jurnal Geologi dan Sumberdaya Mineral, 24(1), 15–24.
Aprilia, A., Rembah, R., & Nurfasiha, N. (2024). Rancangan teknis penambangan dan penjadwalan produksi jangka pendek pada penambangan bijih nikel. Mining Science and Technology Journal, 3(1), 11–19. https://doi.org/10.54297/minetech-journal.v3i1.550
Arianto, D., Misdiyanta, P., & Pangacella Putra, B. (2020). Penjadwalan produksi dan perancangan sequence penambangan batubara. Mining Insight, 1(1), 21–31.
Blom, M., Pearce, A. R., & Stuckey, P. J. (2019). Short-term planning for open pit mines: A review. International Journal of Mining Science and Technology, 29(5), 691–702. https://doi.org/10.1080/17480930.2018.1448248
Deloitte. (2021). Rolling forecasts and continuous planning: A guide to agile financial planning. Deloitte Insights.
Dzakir, L. O., Nurkhalis, M., Dullah, Y., La Ode, P., Yudha, W., Hilman, L. M., Kurnia, M., Kadar, I., Ramadhan, A., Shaddad, M., Karnoha, M., Amir, I. S., & Ambarsari, A. (2023). Buku teknis penambangan nikel. Tohar Media.
Dzakir, L. O., Shaddad, A. R., Syahrul, Kurnia, H., Aldiyansyah, A., Pranata, Y. L. O., Amir, M. K., Bakri, S., Kadar, M. I., & Mahmudah, N. (2024). Buku rekayasa perencanaan tambang. Tohar Media.
Hariyadi, S. (2018). Perencanaan sequence penambangan pada tambang terbuka untuk optimalisasi produksi. Jurnal Teknologi Pertambangan, 4(2), 45–52.
Imana, M. Y., Deniyatno, D., Kadar, M. I., & Mustofa, M. (2023). Perancangan pit dan sequence penambangan nikel. Jurnal Riset Teknologi Pertambangan (J-Ristam), 3(2), 57–68.
PausPaus, L. I., Sidiq, H., & Mukarrom, F. (2022). Kajian teknis produktivitas alat gali-muat dan alat angkut dalam pencapaian target produksi bijih nikel. Prosiding ReTII, 39–47.
Rachmadiani, S. I., Sudiyanto, A., Cahyadi, T. A., Inmarlinianto, I., Winda, W., & Darwis, D. (2021). Analisis kebutuhan alat gali-muat dan alat angkut pada penambangan bijih nikel. Jurnal Pertambangan dan Lingkungan, 2(2), 19–25. https://doi.org/10.31764/jpl.v2i2.6149
AMC Consultants. (2023). Short-term mine planning: What is it and why is it important.
Hartman, H. L., & Mutmansky, J. M. (2015). Introductory mining engineering. John Wiley & Sons.
Nadeak, R. (2024). Rancangan sequence penambangan untuk memenuhi target produksi bulanan. Jurnal Teknik Pertambangan.
Lubis, M. G. (2019). Perancangan teknis tambang bauksit. Jurnal Rekayasa Tambang.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 JURAL RISET RUMPUN ILMU TEKNIK

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
_001.jpg)