Perancangan Mine Sequence untuk Mendukung Target Produksi Bulan April pada Tambang Nikel Laterit Pit Hill16 PT Hillconjaya Sakti

Authors

  • Irga loti Rante Universitas Palangka Raya
  • I Putu Putrawiyanta Universitas Palangka Raya
  • Noveriady Noveriady Universitas Palangka Raya
  • Nuansa Mare Apui Ganang Universitas Palangka Raya
  • Yunida Iashania Universitas Palangka Raya

DOI:

https://doi.org/10.55606/jurritek.v5i2.8903

Keywords:

Laterite Nickel Mining, Mine Sequence, Production Target, Productivity, Rolling Plan

Abstract

This study is motivated by the discrepancy between production targets and actual field performance caused by dynamic operational conditions, such as equipment productivity and effective working time. The objective of this research is to redesign the production target and develop a more realistic mine sequence using a rolling plan approach at Pit Hill16. The method includes analyzing the productivity of loading and hauling equipment based on cycle time data, calculating effective working time, and determining production targets using the rolling plan method. Furthermore, mine sequence design is developed based on the adjusted production targets. The results indicate that the productivity of loading equipment is 241.98 BCM/hour for the EC480DL excavator and 123.27 BCM/hour for the EC210DL excavator, while hauling equipment productivity is 40.24 BCM/hour. The April production target based on the rolling plan is 275,913 BCM, which can be achieved through mine sequence design with a volume of 277,839 BCM, resulting in a difference of +1,926 BCM, still within acceptable planning tolerance. Therefore, the rolling plan approach is proven to produce a more adaptive and realistic mining plan under actual field conditions.

Downloads

Download data is not yet available.

References

Anwar, H., Setiawan, B., & Firmansyah, R. (2023). Estimasi kadar bijih nikel laterit menggunakan pendekatan geostatistik pada tambang terbuka. Jurnal Geologi dan Sumberdaya Mineral, 24(1), 15–24.

Aprilia, A., Rembah, R., & Nurfasiha, N. (2024). Rancangan teknis penambangan dan penjadwalan produksi jangka pendek pada penambangan bijih nikel. Mining Science and Technology Journal, 3(1), 11–19. https://doi.org/10.54297/minetech-journal.v3i1.550

Arianto, D., Misdiyanta, P., & Pangacella Putra, B. (2020). Penjadwalan produksi dan perancangan sequence penambangan batubara. Mining Insight, 1(1), 21–31.

Blom, M., Pearce, A. R., & Stuckey, P. J. (2019). Short-term planning for open pit mines: A review. International Journal of Mining Science and Technology, 29(5), 691–702. https://doi.org/10.1080/17480930.2018.1448248

Deloitte. (2021). Rolling forecasts and continuous planning: A guide to agile financial planning. Deloitte Insights.

Dzakir, L. O., Nurkhalis, M., Dullah, Y., La Ode, P., Yudha, W., Hilman, L. M., Kurnia, M., Kadar, I., Ramadhan, A., Shaddad, M., Karnoha, M., Amir, I. S., & Ambarsari, A. (2023). Buku teknis penambangan nikel. Tohar Media.

Dzakir, L. O., Shaddad, A. R., Syahrul, Kurnia, H., Aldiyansyah, A., Pranata, Y. L. O., Amir, M. K., Bakri, S., Kadar, M. I., & Mahmudah, N. (2024). Buku rekayasa perencanaan tambang. Tohar Media.

Hariyadi, S. (2018). Perencanaan sequence penambangan pada tambang terbuka untuk optimalisasi produksi. Jurnal Teknologi Pertambangan, 4(2), 45–52.

Imana, M. Y., Deniyatno, D., Kadar, M. I., & Mustofa, M. (2023). Perancangan pit dan sequence penambangan nikel. Jurnal Riset Teknologi Pertambangan (J-Ristam), 3(2), 57–68.

PausPaus, L. I., Sidiq, H., & Mukarrom, F. (2022). Kajian teknis produktivitas alat gali-muat dan alat angkut dalam pencapaian target produksi bijih nikel. Prosiding ReTII, 39–47.

Rachmadiani, S. I., Sudiyanto, A., Cahyadi, T. A., Inmarlinianto, I., Winda, W., & Darwis, D. (2021). Analisis kebutuhan alat gali-muat dan alat angkut pada penambangan bijih nikel. Jurnal Pertambangan dan Lingkungan, 2(2), 19–25. https://doi.org/10.31764/jpl.v2i2.6149

AMC Consultants. (2023). Short-term mine planning: What is it and why is it important.

Hartman, H. L., & Mutmansky, J. M. (2015). Introductory mining engineering. John Wiley & Sons.

Nadeak, R. (2024). Rancangan sequence penambangan untuk memenuhi target produksi bulanan. Jurnal Teknik Pertambangan.

Lubis, M. G. (2019). Perancangan teknis tambang bauksit. Jurnal Rekayasa Tambang.

Downloads

Published

2026-05-03

How to Cite

Irga loti Rante, I Putu Putrawiyanta, Noveriady Noveriady, Nuansa Mare Apui Ganang, & Yunida Iashania. (2026). Perancangan Mine Sequence untuk Mendukung Target Produksi Bulan April pada Tambang Nikel Laterit Pit Hill16 PT Hillconjaya Sakti. JURAL RISET RUMPUN ILMU TEKNIK, 5(2), 377–388. https://doi.org/10.55606/jurritek.v5i2.8903