Analisis Kesesuaian Realisasi di Lapangan terhadap Rencana Penambangan Bulan Maret 2025 di Pit P3BK4 PT Tama Raya provinsi Kalimantan timur
DOI:
https://doi.org/10.55606/jurritek.v5i1.7443Keywords:
mining suitability, overcut–undercut, PT Tama Raya, production realization, sequenceAbstract
This study was conducted to evaluate the level of conformity between actual mining activities in March 2025 and the monthly sequence design plan at PT Tama Raya's P3000BK14 pit. The evaluation focused on geometric deviations, volume achievement, and changes in field conditions that influenced these discrepancies. The data used included the sequence design, actual topography from the TLS (Low-Scale Land Survey), and weekly production realizations. The results showed significant discrepancies between the planned and actual operations in weeks 2 and 4, primarily in the form of overcuts, undercuts, non-designed contour changes, thinning of the coal seam, and hydrological obstacles such as ponding and unstable drainage. The R2 sequence redesign in week 4 proved to improve the overburden excavation flow but did not fully restore coal access due to persistent geological and water conditions. These findings emphasize the need for more rapid topographic updates, more intensive water handling, and interdepartmental coordination to ensure better synchronization of plans and operations.
Downloads
References
Ginting, S. D., Yulanda, Y. A., & Zahar, W. (2023). Evaluasi Rencana Penambangan Tahunan 2022 Untuk Optimalisasi Target Produksi Di Pt Jambi Prima Coal Desa Pamusiran. Jurnal Sains dan Teknologi: Jurnal Keilmuan dan Aplikasi Teknologi Industri, 23(1), 122. https://doi.org/10.36275/stsp.v23i1.600
https://doi.org/10.36275/stsp.v23i1.600
Gupta, M. D., & Pal, S. K. (2016). Optimizing Mining Processes: The Future of Mining. Wiley. https://doi.org/10.1002/9781119094161
Harris, C. M., & Hall, D. R. (2008). Underground Mining Methods: Engineering Fundamentals and International Case Studies. Elsevier.
Hartman, H. L., & Mutmansky, J. M. (2002). Introductory Mining Engineering (2nd edition). John Wiley & Sons.
Hustrulid, W., & Kuchta, M. (2006). Open Pit Mine Planning and Design. Taylor & Francis.
Jackson, G. D., & O'Neill, P. A. (2017). Mine Ventilation Design. Springer. https://doi.org/10.1007/978-3-319-40294-3
Kumar, R. P., & Singh, K. (2020). Environmental Impact of Mining. CRC Press. https://doi.org/10.1201/9780429293893
Liu, J., & Zhang, X. (2019). Geotechnical Considerations in Open Pit Mining. Springer. https://doi.org/10.1007/978-3-319-95713-2
Musmualim, Ibrahim, E., & Suwardi. (2014). Rekonsiliasi Penambangan antara Rencana Penambangan Bulanan dengan Realisasi di Tambang Swakelola B2 PT Bukit Asam. Jurnal Teknik Pertambangan, 4(1), 1–10.
Musmualim, Musmualim, Ibrahim, E., & Suwardi, Fuad Rusydi. (2015). Rekonsiliasi Penambangan Antara Rencana Penambangan Bulanan Dengan Realisasi Di Tambang Swakelola B2 PT. Bukit Asam (Persero), Tbk. Jurnal Ilmu Teknik Sriwijaya, 3(1).
Projosumarto, P. (2004). Perencanaan dan Pengendalian Produksi Tambang. (Nama penerbit diisi sesuai sumber aslinya).
Schafhirt, M. L. (2018). Fundamentals of Mining Engineering. Elsevier.
Singh, A., & Sharma, N. (2019). Mining Economics and Management. Routledge. https://doi.org/10.1201/9780429271494
Smith, M., & Johnson, L. R. (2021). Mining Operations and Technology. Springer. https://doi.org/10.1007/978-3-030-33251-2
Turner, B., & Foster, M. (2015). Advanced Mining Techniques. Cambridge University Press.
Whelan, J. A., & Abbott, R. P. (2020). Mining Technology and Innovation. Wiley-VCH. https://doi.org/10.1002/9781119607961
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 JURAL RISET RUMPUN ILMU TEKNIK

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
_001.jpg)