Analisis Permasalahan Pembebasan Lahan pada Pekerjaan Pembangunan Jalan
DOI:
https://doi.org/10.55606/jurritek.v5i2.7729Keywords:
Compensation, Infrastructure Development, Institutional Coordination, Land Acquisition, Road ConstructionAbstract
An essential stage in road infrastructure development is land acquisition, which frequently causes project delays due to its complex legal, social, and economic challenges. This study aims to identify the factors that hinder the land acquisition process in the Manado Outer Ring Road (MORR) 3 Phase 4 Construction Project and to assess how these constraints affect the progress of construction activities. The research was conducted using a qualitative case study approach, with data collected through field observations, document reviews, and interviews. The findings indicate that delays in land acquisition are caused by discrepancies in legal status and land ownership, differing perceptions of compensation value, insufficient public socialization, and weak institutional coordination. These issues lead to disruptions in the construction schedule and potential increases in project costs. The study demonstrates that land acquisition necessitates a more cohesive strategy, facilitated by enhanced communication and community engagement, fortified land acquisition management frameworks, and precise verification of ownership data. The results indicate that there must be broader mitigation strategies to prevent similar challenges in future infrastructure projects.
Downloads
References
Ahmed, S., Azhar, S., Kappagntula, P., & Gollapudi, D. (2003). Delays in construction: A brief study of the Florida construction industry. In Proceedings of the 39th Annual ASC Conference (p. 293). Clemson University.
Asmi, A., Rahmadi, M. G., & Djamaris, A. (2025). Risk analysis of construction delays in high-rise projects. International Journal of Multidisciplinary Research and Analysis, 8(8), 4644–4648. https://doi.org/10.47191/ijmra/v8-i08-28
Dipohusodo, I. (1996). Manajemen proyek & konstruksi (Jilid 2). Kanisius.
Kementerian Pekerjaan Umum dan Perumahan Rakyat. (2023). Peraturan Menteri PUPR Nomor 5 Tahun 2023 tentang pedoman pengadaan tanah dan pengelolaan aset infrastruktur jalan. Kementerian PUPR.
Maria, S. W. S. (2005). Kebijakan pertanahan: Antara regulasi dan implementasi. Kompas.
Musra, A. (2014). Faktor-faktor penentu keterlambatan pembangunan Jalan Lingkar Utara Kota Solok. Jurnal Pembangunan Wilayah dan Kota, 10(1), 70–82. https://doi.org/10.14710/pwk.v10i1.7634
Nugraha, D. (2019). Analisis konflik dalam pembebasan lahan proyek infrastruktur. Jurnal Infrastruktur dan Pembangunan Daerah, 7(2), 45–56.
Peraturan Presiden Republik Indonesia Nomor 71 Tahun 2012 tentang penyelenggaraan pengadaan tanah bagi pembangunan untuk kepentingan umum. (2012).
Project Management Institute. (2021). A guide to the project management body of knowledge (PMBOK® Guide) (7th ed.). Project Management Institute.
Sadono, S. (2006). Faktor-faktor yang menghambat pelaksanaan pengadaan tanah terhadap kinerja waktu proyek pembangunan jalan tol (Tesis). Universitas Indonesia.
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in construction projects. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007
Sarjita. (2005). Teknik dan strategi penyelesaian sengketa pertanahan. Tugu Jogja Pustaka.
Soeharto, I. (1995). Manajemen proyek: Dari konseptual sampai operasional. Erlangga.
Sutopo, H. B. (2010). Metodologi penelitian kualitatif: Dasar teori dan terapannya dalam penelitian sosial. UNS Press.
Undang-Undang Republik Indonesia Nomor 2 Tahun 2012 tentang pengadaan tanah bagi pembangunan untuk kepentingan umum. (2012).
Wirabakti, E., et al. (2014). Studi faktor-faktor keterlambatan proyek konstruksi bangunan gedung. Jurnal Konstruksi, 6(1).
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 JURAL RISET RUMPUN ILMU TEKNIK

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
_001.jpg)