Analisis Perencanaan Mutasi Trafo pada Gardu CMY dengan Metode Least Square untuk Keandalan Sistem Distribusi di PT PLN (Persero) ULP Labuan
DOI:
https://doi.org/10.55606/jurritek.v5i1.7547Keywords:
Distribution Transformer, Least Square Method, Load Growth Prediction, Overload Analysis, Transformer ReplacementAbstract
Distribution transformers play a crucial role in delivering electrical energy from the distribution system to consumers to ensure power quality and supply continuity. However, in practice, overload conditions often occur due to increasing demand and load growth that exceed the transformer’s rated capacity. This situation can lead to reduced efficiency, increased power losses, and accelerated equipment aging. This study aims to analyze the performance of the CMY distribution transformer at PT PLN (Persero) ULP Labuan, which operates beyond its nominal capacity, and to propose an alternative solution through transformer mutation, namely the replacement of the existing unit with a transformer of more appropriate capacity based on load analysis results. The Least Square Method is employed to predict future load growth and determine the projected time when the transformer will again experience overload after the mutation. The results indicate that the existing 100 kVA transformer is overloaded and should be replaced with a 160 kVA unit. After the mutation, the loading percentage decreases significantly, the transformer’s lifespan is extended, and the reliability of the distribution system improves. Furthermore, the Least Square prediction suggests that the new transformer may experience overload again in future years if no further planning is carried out. Therefore, transformer mutation can be considered an effective and medium-term solution to enhance and maintain the reliability of the electrical distribution system within the operational area of PT PLN (Persero) ULP Labuan.
Downloads
References
Anisah, S., & Khaizairani, A. (2018). Analisis perbaikan tegangan ujung pada jaringan tegangan menengah 20 kV Express Trienggadeng daerah kerja PT PLN (Persero) Area Sigli Rayon Meureudu dengan simulasi E-Tap Edge. Journal of Electrical and System Control Engineering, 2(1). https://doi.org/10.31289/jesce.v2i1.1916
Anisah, S., Tharo, Z., & Rahma Daniati, E. (2024). Analysis of additioning insert transformers in 20 kV networks in improving voltage quality. Journal of Information Technology and Computer Science (Intecoms), 7(2).
Anshar, C. N. (2023). Studi analisa perkiraan umur transformator distribusi 20 kV akibat pembebanan. Jurnal Teknik, Komputer, Agroteknologi dan Sains, 1(2). https://doi.org/10.56248/marostek.v1i2.26
Arifyanto, D. (2023). Analisis penentuan letak trafo distribusi pada penyulang Walmas menggunakan ETAP Power Station 12.6.0. Jurnal Teknologi Elekterika, 20(1). https://doi.org/10.31963/elekterika.v20i1.4502
Capulong, C. D. B., Camat, P. K., Gonzales, P. B., Bunoan, K. G. O., Tolentino, A. C., Gomez, R. H., Jr., & Favorito, R. M. (2025). Analysis of failure rate due to transformer loadings of commonly used transformers in Porac substation. Journal of Science Technology and Engineering Research (JSTER), 6(2), 107–117. https://doi.org/10.53525/jster.1722805
Dewi, T. P., & Lubis, Z. (2024). Analysis of the decrease in insulation resistance of pin type porcelain insulation at the ULP Ampera of PT PLN (Persero). Jurnal Teknik Elektro, 6(1), 1–11. https://doi.org/10.52005/fidelity.v6i1.184
Guo, W., Liu, J., Ma, J., & Lan, Z. (2025). Short-term power load forecasting using adaptive mode decomposition and improved least squares support vector machine. Energies, 18(10), Article 2491. https://doi.org/10.3390/en18102491
Iria, J., Heleno, M., & Candoso, G. (2019). Optimal sizing and placement of energy storage systems and on-load tap changer transformers in distribution networks. Applied Energy, 250. https://doi.org/10.1016/j.apenergy.2019.04.120
Pabla, A. S. (2019). Electric Power Distribution (7th ed.). Tata McGraw Hill.
Pebrisasvian, A. T., & Karim, S. (2021). Analisa sisip transformator distribusi terhadap perbaikan overload dan tegangan ujung Gardu BNS-0126 di PT PLN (Persero) UP3 Barabai. Jurnal EEICT (Electric Electronic Instrumentation Control Telecommunication), 4(2). https://doi.org/10.31602/eeict.v4i2.6585
PT PLN (Persero). (2007). Spesifikasi Transformator Distribusi: SPLN D3.002-1:2007. Jakarta: PT PLN.
Sarikin, R. C. D. (2019). Analisis susut daya dan energi pada jaringan distribusi di PT PLN (Persero) Rayon Panakkukang. Jurnal Teknologi Elekterika, 16(1). https://doi.org/10.31963/elekterika.v16i2.1575
Sutjipto, R., Sungkowo, H., Mukti Khristiana, H., Dhesah Kharisma, D., Putra Fauzy, G., & Agiesta Anjali, F. (2025). Implementasi Least Square Method. (n.d.).
Syukri, S., Asyadi, T. M., Muliadi, M., & Moesnadi, F. (2022). Analisa pembebanan transformator distribusi 20 kV pada penyulang LS5 Gardu LSA 249. Jambura Journal of Electrical and Electronics Engineering, 4(2). https://doi.org/10.37905/jjeee.v4i2.14500
Wahyudi Widiatmika, K., Arta Wijaya, I. W., & Setiawan, I. N. (2018). Analisis penambahan transformator sisipan untuk mengatasi overload pada transformator DB0244 di penyulang Sebelanga. Jurnal Spektrum, 5(2). https://doi.org/10.24843/spektrum.2018.v05.i02.p03
Zhang, W., Liu, S., Li, M., Bao, H., Yuan, S., & Cheng, X. (2025). A method for load forecasting of distribution transformers based on parameter-efficient fine-tuning of large language models in power system. Processes, 13(9), Article 2986. https://doi.org/10.3390/pr13092986
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2025 JURAL RISET RUMPUN ILMU TEKNIK

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
_001.jpg)