Simulasi Analisa Aliran Daya Pekerjaan Evakuasi Daya Penyulang Kintamani di PT PLN (Persero) UP3 Bali Timur dengan Software ETAP
DOI:
https://doi.org/10.55606/jurritek.v5i2.8744Keywords:
ETAP, Losses, Payback Period, Power Evacuation, Voltage ProfileAbstract
This study aims to analyze the technical and economic impact of power evacuation work on the 20 kV distribution system at PT PLN (Persero) UP3 East Bali. The main problem studied is the high losses and poor voltage profile on the downstream side of the Kintamani feeder. The method used is load flow simulation using ETAP software with a comparative approach to conditions before and after power evacuation. The results showed that the active losses decreased from 1.017 MW to 0.626 MW (efficiency 38.45%), accompanied by an increase in the end voltage from 16.32 kV to 18.72 kV and 19.38 kV, thus meeting the SPLN 1:1995 standard. The reduction in losses resulted in energy savings of 3,425,160 kWh/year. From the economic side, a payback period (PBP) of 1.40 years was obtained, which shows that the project is financially feasible. In addition, the improvement of network performance also contributes to the reliability of the distribution system and the continuity of the distribution of electrical energy to customers. Thus, power evacuation work has been proven to be effective in improving power distribution efficiency, improving voltage quality, and providing significant economic benefits.
Downloads
References
Abdi, H. (2024). Power system analysis using the ETAP software: A comprehensive review. Journal of Energy Management and Technology (JEMT), 8(3), 250.
Blank, L., & Tarquin, A. (2014). Basics of engineering economy. McGraw-Hill.
Cavus, M. (2024). Integration of smart grids, distributed generation, and cybersecurity: Strategies for securing and optimizing future energy systems (pp. 0–34).
Gönen, T. (2014). Electrical power distribution engineering. CRC Press.
Hasanah, A. W., Koerniawan, T., & Yuliansyah, Y. (2019). Kajian kualitas daya listrik PLTS sistem off-grid di STT-PLN. Energi & Kelistrikan, 10(2), 93–101.
Ihsan, A., Erhaneli, E., & Anthony, Z. (2023). Analisis pengaruh jarak antar fasa terhadap rugi korona pada saluran udara tegangan ekstra tinggi 275 kV. Emitor: Jurnal Teknik Elektro, 22(2), 158–165.
Junito, R., Putra, D. E., Yani, R. A., & Nofiansah. (2025). Pengaruh fluktuasi tegangan akibat blackout pada saluran distribusi 20 kV terhadap kinerja arrester. Jurnal Ampere, 10(1), 117–123.
Kadir, A. (2000). Distribusi dan utilisasi tenaga listrik. UI Press.
Khoirunnisa, N., Inayah, N., Wiherdiansyah, F., Adyano, I. K. D., & Aribowo, D. (2024). Studi literatur tentang jenis dan penyebab gangguan pada saluran transmisi. Surya Teknika, 11, 569–573.
Kisworo, D., Utomo, A. P., Saputra, Y. A., & Stefanie, A. (2025). Analisis rugi-rugi daya pada penyulang Sukamulya di PT PLN (Persero) UP3 Purwakarta dengan menggunakan software ETAP. Journal of Informatics and Electrical Engineering, 7(1), 46–54.
Kundur, P. S., & Malik, O. P. (2022). Power system stability and control. McGraw-Hill Education.
Manembu, P. D., Kewo, A., & Singgeta, R. L. (2021). Pemodelan data konsumsi listrik melalui sistem intelligensia smart-meter. Jurnal Teknik Elektro dan Komputer, 10(2), 153.
Marisa, U. L. P., & Humena, S. (2025). Analisis rekonfigurasi jaringan distribusi 20 kV PLN ULP Marisa. Jurnal Teknik Elektro, 7, 295–301.
Mugandi, N. M. (2022). Pemeliharaan jaringan distribusi SUTM 20 kV (penyulang Mawar) di PT PLN ULP Kampar. Indonesian Journal of Electrical Engineering and Renewable Energy, 2(2), 85–95.
Muhtar, A., Iwan, Antarissubhi, & Suryani. (2022). Analisis rugi daya jaringan distribusi primer PT PLN ULP Sengkang Sulawesi Selatan.
Nugroho, T. W., Mustaqim, I., & Wardhana, A. S. J. (2025). Studi kualitas daya listrik (power quality) di bangunan gedung XYZ. Jurnal Informatika dan Teknik Elektro Terapan, 13(2).
Pan, H., Dou, Z., Cai, Y., Li, W., Lei, X., & Han, D. (2020). Digital twin and its application in power system.
Panggabean, M., Surapati, A., & Rosa, M. K. A. (2022). Pengaruh total harmonic distortion (THD) terhadap pembacaan kWh meter semi digital. Jurnal Amplifier: Jurnal Ilmiah Bidang Teknik Elektro dan Komputer, 12(1), 25–33.
Prasad, B. M., Ganesh, P., Vinay Kumar, K., Mohanarao, P. A., Swathi, A., & Manoj, V. (2024). Renewable energy integration in modern power systems: Challenges and opportunities. E3S Web of Conferences, 591.
PT PLN (Persero). (1995). Tegangan-tegangan standar (SPLN 1:1995).
PT PLN (Persero). (2010). Standar konstruksi sambungan tenaga listrik.
Putra, D. E., Riswanto, Y., & Komaini, A. (2021). Investigasi overload transformator distribusi 20 kV di unit layanan pelanggan Pangkalan Balai PT PLN (Persero). Seminar Nasional AVoER XIII, 378–383.
Rahmaan, A. B. A., Penangsang, O., & Aryani, N. K. (2016). Optimalisasi penempatan kapasitor bank untuk memperbaiki kualitas daya pada sistem kelistrikan PT Semen Indonesia Aceh menggunakan metode genetic algorithm (GA). Jurnal Teknik ITS, 5(2).
Ramadhan, R. (2023). Analisis load flow pada kilang dan utilitas PPSDM MIGAS. Jurnal Nasional Pengelolaan Energi MigasZoom, 5(1), 1–10.
Saadat, H. (1999). Power system analysis.
Sahbana, M. F., & Suheta, T. (2021). Perencanaan saluran kabel tegangan menengah pada jaringan distribusi 20 kV di penyulang Pasar Kembang. SinarFe7, 4(1), 118–120.
Suhadi. (2008). Teknik distribusi tenaga listrik jilid III (Buku ajar). Direktorat Pembinaan Sekolah Menengah Kejuruan.
Syaputra, A., & Ervianto, E. (2017). Perhitungan rugi daya saluran distribusi primer 20 kV feeder Adi Sucipto di GI Garuda Sakti dengan metode ladder iterative technique. JOM FTEKNIK, 4(1), 1–10.
Wasahua, S., Rikumahu, J. J., & Kastanja, A. J. (2023). Analisa penyebab gangguan jaringan distribusi GI Sirimau PT PLN (Persero) area Ambon menggunakan metode FTA (fault tree analysis). Jurnal ELKO (Elektrikal dan Komputer), 2(2).
Wood, A. J., & Wollenberg, B. (1996). Power generation, operation and control (2nd ed.).
Yansuri, D. S., Subianto, S., & Akbar, M. A. (2021). Evaluasi jenis kabel dari tembaga ke aluminium untuk distribusi power supply 20 kV coal conveyor. Jurnal Teknik Elektro, 11(2), 9–17.
Yusiran, Y., & Hasanudin, H. (2025). Analisis pengaruh ketidakseimbangan beban terhadap rugi-rugi daya dan efisiensi transformator step down 20 kV/400 V. Jurnal Penelitian Inovatif, 5(3), 2113–2120.
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 JURNAL RISET RUMPUN ILMU TEKNIK

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
_001.jpg)