Optimalisasi Penjadwalan Perbaikan Kapal X di PT XYZ Menggunakan Critical Path Method

Authors

  • Revian Devo Aryton Putra Universitas Pembangunan Nasional “Veteran” Jawa Timur
  • Yekti Condro Winursito Universitas Pembangunan Nasional “Veteran” Jawa Timur

DOI:

https://doi.org/10.55606/jurritek.v5i1.8182

Keywords:

CPM, Critical Path Method, Project Scheduling, Ship Repair, Shipyard Industry

Abstract

Punctuality is a crucial factor in ship repair projects because it directly affects operational efficiency, project costs, and the utilization rate of shipyard facilities. Delays in work completion can lead to increased costs, disruption of ship operational schedules, and decreased shipyard productivity. Therefore, this study aims to analyze and optimize the repair scheduling of Ship X at PT XYZ using the Critical Path Method (CPM). The research data were obtained from the actual project schedule compiled using Microsoft Project software, including the duration of each activity and the dependency relationships between tasks. The analysis results show that the project has one main critical path with a total duration of 74 hours. Most activities are on the critical path with a float value of 0 hours, while the Non-Destructive Test Penetrant Testing activity has a time slack of 1 hour. The application of the CPM method has proven effective in identifying critical activities, improving schedule control, and supporting managerial decision-making in optimizing ship repair projects.

 

Downloads

Download data is not yet available.

References

Agus, M., Priana, E. S., & Dewi, S. (2025). Optimasi penjadwalan proyek menggunakan metode Critical Path Method (CPM). Rangkiang Jurnal, 1(2), 228–236.

Badriyah, P. A., Tjakra, J., & Malingkas, G. Y. (2025). Analisis Manajemen Waktu Dengan Critical Path Method (CPM) Pada Proyek Pembangunan Reservoir SPAM Kota Manado. TEKNO, 23(91), 739–751.

Fakhrija, M. F., Mulyatno, I. P., & Zakki, A. F. (2020). Studi penjadwalan ulang pekerjaan reparasi pada kapal MT. Asumi XXVI dengan network planning dan Critical Path Method. Jurnal Teknik Perkapalan, 8(3).

Heizer, J., Render, B., Munson, C. L., & Griffin, P. (2020). Operations management: Sustainability and supply chain management.

Kerzner, H. (2025). Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons.

Kurniawan, R., & Putra, A. (2020). Penerapan critical path method dalam pengendalian waktu proyek. Jurnal Teknik Industri, 11(3), 145–152.

Moder, J. J. (1983). CR Phillips and EW Davis. Project Management with CPM, PERT and Precedence Diagramming.

Render, B., Stair, R. M., Hanna, M. E., & Hale, T. S. (2018). Quantitative analysis for management (13th ed.). Pearson Education.

Runtuwarow, A. M., Pratasis, P. A. K., & Tjakra, J. (2025). Analisis penjadwalan waktu pada proyek konstruksi ruang praktik siswa SMKN 4 Manado menggunakan Critical Path Method (CPM). TEKNO: Jurnal Teknik, 23(93).

Shtub, A. (2013). Project management: Processes, methodologies, and economics.

Sinurat, F., & Misdalena, F. (2024). Analisis manajemen proyek dengan metode Critical Path Method (CPM) pada proyek pembangunan Gedung Chandra Tanjung Karang. Jurnal Konstruksi, 22(2).

Stevenson, W. J. (2021). Operations management (14th ed.). McGraw-Hill Education.

Suci Anggraini. (2024). Implementation of the Critical Path Method in Optimizing the Orthodox Black Tea Processing. Zero: Jurnal Sains, Matematika, dan Terapan, Volume 14, hlm. 85–88.

Suramli, S., Rachman, K. A., Dewi, N. F., Novianda, D. S., & Surahman, S. (2025). Critical path analysis scheduling project with critical path method (CPM) using application Microsoft Project on type 78 house construction project. Enrichment: Journal of Management, 15(2), 73–81.

Wignarajah, S., & Perera, B. (2019). Application of critical path method (CPM) in ship repair project scheduling. International Journal of Maritime Engineering, 161(A3), 1–10.

Downloads

Published

2026-01-26

How to Cite

Revian Devo Aryton Putra, & Yekti Condro Winursito. (2026). Optimalisasi Penjadwalan Perbaikan Kapal X di PT XYZ Menggunakan Critical Path Method. JURAL RISET RUMPUN ILMU TEKNIK, 5(1), 684–691. https://doi.org/10.55606/jurritek.v5i1.8182