Analisis Penjadwalan Pekerjaan Tanah (Land Clearing) Menggunakan Precedence Diagram Method, Pada Proyek Perumahan Bunda Asri Karangdagangan, Jombang

Authors

  • Andim Rendy Setiawan Universitas Hasyim Asy’ari
  • Totok Yulianto Universitas Hasyim Asy’ari
  • Titin Sundari Universitas Hasyim Asy’ari
  • Rahma Ramadhani Universitas Hasyim Asy’ari
  • Meriana Wahyu Nugroho Universitas Hasyim Asy’ari

DOI:

https://doi.org/10.55606/jurritek.v2i2.1735

Keywords:

Heavy Equipment, PDM, Excavation, Piles, land clearing, WBS

Abstract

Land work (land clearing) in the Bunda Asri housing development project was carried out to meet the contours of the land so as to reach the planned contours, according to housing project data the volume of excavation work (cut) was 374,758.15 m³ and heap (fill) was 323,320.39 m³. The volume of excavation (cut) and embankment (fill) is divided into five sections of the earthwork area with a duration of work completion of 90 calendar days. Time constraints are the reason for project or work activities to be right on plan. Scheduling in this study uses the precedence diagram method (PDM) and is assisted by Microsoft Project software. A network that has definite dependencies and can be used in projects with overlapping activities between one another's work is called PDM. The results of the research analysis used the PDM method for the construction of Bunda Asri housing, namely 81 calendar days. which is faster than the estimate of the housing developer which lasted 90 calendar days. This happened because the grouping of work with a work breakdown structure and predecessors reduced the duration time and did not precede each other among other works.

References

Andim Rendy S, T. Y. M. W. N. (2022). Analisa Kapasitas Produksi Alat Berat Excavator Dan Dump Truck Pada Pekerjaan Persiapan Lahan Perumahan. 2(1), 20–29.

Basyar, A. C., Nugroho, M. W., Yulianto, T., & ... (2021). Produktivitas Pekerjaan Plat Lantai Internasional Terminal 1 Bandara Juanda Surabaya. Jurnal Ilmiah …, 1(1), 23–32.

Bejasekto, S. (2020). Analisis Produktivitas Alat Berat Pada Jalan Impeksi Opas Indah (Analysis of Productivity Needs for Heavy Equipment in the Road of Inspection Opas Indah). Tugas Akhir Analisis, 95. https://dspace.uii.ac.id/handle/123456789/12129

Deko Sanjaya & Syahrizal. (2014). Studi Perbandingan Penjadwalan Proyek Metode Line Of Balance (Lob) Dan Precedence Diagram Method (Pdm) Pada Pekerjaan Berulang (Repetitif) (Studi Kasus Proyek Perumahan Maysa Tamansari Residence).

Ir. Irika Widiasanti, M.T & Lenggogeni, M. . (2013). Manajemen Konstruksi (Pipih Latifah (ed.); Cetakan 1). Dicetak oleh PT Remajan Rosdakarya Offset - Bandung.

Manumpil, T. O., Mangare, J. B., & Arsjad, T. T. (2022). Analisis Penjadwalan Proyek Menggunakan Metode PDM Dengan Konsep Cadangan Waktu Pada Proyek Pembangunan Gedung Dokter Polisi Rumah Sakit Bhayangkara Kota Manado. 20.

Putra, W. R., Ridwan, A., Cahyo, Y., & Candra, A. I. (2020). Studi Pelaksanaan Kinerja Percepatan Waktu Pada Proyek Pembangunan Gedung Bank Darah Rumah Sakit Dr. Soedomo. Jurnal Manajemen Teknologi & Teknik Sipil, 3(1), 76. Https://Doi.Org/10.30737/Jurmateks.V3i1.892

Saskia, L. N., Rio, W. Y., Damayanti, L., & Hum, M. (2020). Analisis Penggunaaan Metode Penjadwalan Line Of Balance Pada Proyek Kosntruksi Repetitif. Jurnal Tugas Akhir Teknik Sipil, 4.

Utami, A. (2018). ANALISIS PENJADWALAN WAKTU PELAKSANAAN PROYEK MENGGUNAKAN METODE LSM (LINIER SCHEDULING METHOD).

Widiasanti, I. Dan L. (2013). / 1 ’ S7 ,. H.

Downloads

Published

2023-08-19

How to Cite

Andim Rendy Setiawan, Totok Yulianto, Titin Sundari, Rahma Ramadhani, & Meriana Wahyu Nugroho. (2023). Analisis Penjadwalan Pekerjaan Tanah (Land Clearing) Menggunakan Precedence Diagram Method, Pada Proyek Perumahan Bunda Asri Karangdagangan, Jombang. JURAL RISET RUMPUN ILMU TEKNIK, 2(2), 63–73. https://doi.org/10.55606/jurritek.v2i2.1735